APeX Center Update: Exterior Walls Are Going Up
The APeX Center is taking another exciting step forward as the exterior walls begin going up on-site. After the early morning concrete slab pour and the completion of major foundation work, this next phase brings a whole new level of progress to the project. What once looked like a prepared construction site is now beginning to take real shape as the building’s exterior walls rise from the slab. The APeX Center Is Starting to Take Shape This stage is always one of the most ex
4 days ago


Breakwater Build Footer Pour: Building a New Home on a Foundation of Faith.
The Breakwater Build has officially reached another major milestone. After completing the demolition of the previous home and preparing the property for new construction, the Talica Design | Build team has now excavated the footers for the new residence. Today, concrete is being poured to create the structural foundation that will support the home for years to come. What Is a Concrete Footer? Concrete footers are one of the most important parts of any new construction project
Jul 13


APeX Center Construction Update: Over 10,000 Square Feet of Concrete Poured
At 3:00 AM, while most of St. Petersburg was still asleep, the job site at the APeX Center came to life.
Crews arrived before sunrise, lights came on, concrete trucks started rolling in,
Jun 24


APeX Center Update: Ready for the Early Morning Slab Pour
Exciting progress continues at the PYCC Wellness Center as we prepare for one of the biggest milestones of the project so far.
Jun 22


The Bali House Reaches New Heights
Progress continues to move quickly at The Bali House, and this custom home is already beginning to take shape.
Since our last update, the structure has risen another level as the team continues building the exterior block walls.
Jun 22


The Axiom Project Reaches a Major Milestone: Slab Pour Day
Exciting progress is underway at the Axiom Project as the Talica Design | Build team reaches another major construction milestone. Today, crews were on site pouring the concrete slab that will serve as the foundation for this future custom home. Using a concrete pumping truck and working with precision throughout the day, the team carefully placed and finished concrete while coordinating every step of the process. A slab pour is one of the most important stages of any build.
Jun 19


APeX Center Update: Infrastructure Taking Shape Beneath the Foundation
With under-slab utilities being completed and concrete overhang forms taking shape, the project is rapidly approaching the next major phase of construction. Each step brings the APeX Center closer to becoming a modern destinatio
Jun 18


Building Progress Continues: Stem Wall Construction Underway at the APeX Center
The transformation of the new wellness center at Pasadena Yacht & Country Club is continuing to take shape as another major construction milestone has officially begun. Talica Design | Build is proud to share the latest progress from the APeX Center project, where stem wall construction is now underway.
May 1


APeX Center Update: Footer Concrete Pour Complete
We’ve officially completed the footer concrete pour, laying the critical foundation that will support the entire structure of this new wellness facility.
Apr 17


APeX Center Project Update: Major Progress on Site & Footers
Following the initial kickoff, Talica Design | Build has completed extensive ground clearing, transforming the site and preparing it for construction. This pha
Apr 7


Breakwater Build: Demolition Begins on a Coastal Transformation
Talica Design | Build begins the Breakwater Build with a full demolition, clearing the way for a modern coastal custom home from the ground
Mar 31


A New Chapter Begins at Pasadena Yacht & Country Club
Talica Design | Build officially breaks ground at Pasadena Yacht & Country Club in Gulfport, kicking off an exciting $18 million renovation. The project includes a redesigned golf course, new floating marina docks, and a 14,000-square-foot wellness center focused on longevity, performance, and luxury living. Follow along as we document this transformation from the ground up.
Mar 20


The Axiom Project Begins: Concrete Footer Pour Day
The Axiom Project is officially underway! Today our team at Talica Design | Build completed a major milestone by pouring the concrete footer
Mar 11


The Bali House Begins: A New Custom Home Build by Talica Design | Build
This week, the team at Talica Design | Build kicked off the foundation for a brand-new custom home project we’re calling The Bali House. As the sun rose over St. Petersburg, Florida, our crew was already hard at work preparing for one of the most exciting milestones in any build: the concrete slab pour.
Mar 10


APeX CENTER RENDERINGS.
These are renderings for the PYC wellness center currently under construction